Job Costing

Riverside Medical Center · Job #2418 · Estimate at Completion

Contract $8,420,000
Working capital available on this job
Drawable against committed, unpaid subcontract balances — cover cost movement before the next lender draw.
Available
$145,000

Cost codes

Original · Committed · Actual · EaC · Variance
Cost codeOriginalCommittedActualEaCVariance
03-3000 Concrete$420,000$438,500$402,100$441,000
$2,500
05-1000 Structural Steel$610,000$598,000$560,300$596,000
+$2,000
15-4000 HVAC$285,000$302,400$268,900$331,500
$29,100
16-0100 Electrical$340,000$351,200$300,450$349,000
+$2,200
09-9000 Interior Finishes$175,000$168,000$92,300$171,000
$3,000
Total$1,830,000$1,858,100$1,624,050$1,888,500$30,400